Market Participants:

Following are some significant dates for the Congestion
Reform Project through August 1. Although we had planned to give you a
schedule through September, dates for significant events after August 1 are
not yet finalized. We will send you information on future dates as it
becomes available.

July 11 Release of Draft Congestion Management Package (
Includes Locational Price Dispersion Study)

July 13-14 Stakeholder meetings to discuss Draft
Congestion Management Package (ISO Headquarters, Folsom)

July 21 Public release of remaining Congestion Management
Package appendices

July 24th Written comments from stakeholders due


July 24th Meeting of Market Surveillance Committee


July 27th Final Congestion Management Package released
to Board

August 1st Board meeting to approve Congestion
Management Package

Please contact me if you have any questions about this
project.

Byron Woertz
Director, Client Relations