From the Risk Management perspective I would like to add the following
comments : UK Power - despite much testing we still have a few production teething problems with the transfer to Enpower and this was the first full live day. The specific issues surrounding the o30m adjustment is being investigated by IT and we hope to have a definitive answer tomorrow. Continental Power - the Portcalc valuation failed 4 times as a result of IT problems resulting is us missing the deadline. Oslo - the officialisation was at 10.56 London time against a deadline of 11.00. James David Hardy 21/11/2000 17:01 To: James New/LON/ECT@ECT cc: Mike Jordan/LON/ECT@ECT, Steve W Young/LON/ECT@ECT, Debbie R Brackett/HOU/ECT@ECT, David Port/Market Risk/Corp/Enron@ENRON, Michael R Brown/LON/ECT@ECT Subject: DPR Adjustments for UK Power James, It appears only the UK Gas MTM made it for the V@R run in Houston today. UK Power: (despite the spotlight being on this feed due to the first run of the new evaluation system) was officialised late and required the below mentioned adjustment. Contintental Power : Officialised late ? Nordic Power : was officialised around 11am London time - the slowness of the current feed to Houston prevented the feed reaching there on time (feed has been rewritten by IT to speed up the process and is currently in UAT) however, it appears the normal time for officialisation this book is around 10.30am which allows the feed to hit to normally hit on time. Appreciate if you could looked into the above. Regards David ---------------------- Forwarded by David Hardy/LON/ECT on 21/11/2000 16:06 --------------------------- Michael Batey 21/11/2000 12:22 To: David Hardy/LON/ECT@ECT cc: Mike Wellings/LON/ECT@ECT Subject: DPR Adjustments for UK Power David We have a topside adjustment to put through of o(30,164,151) against South Western Electricity plc. This is due to PD Deal E000535, Peer ID 41957 being valued in EnPower when it was supposed to be excluded from the MTM. Regards Mike
|