John, thanks for questioning this. Lynn

-----Original Message-----
From: Buchanan, John
Sent: Thursday, August 30, 2001 11:50 AM
To: ETS Solution Center,
Cc: Rich, Sue; Blair, Lynn; Hottap HelpDesk; Corman, Shelley; Holmes, Bradley; Medeles, Gerry
Subject: RE: ETS Corporate Change Control Items

Is there a reason why the work on September 4th to the VPN can not be done during the normal maintenance window provided for this type of outage?
This outage is presently planned during core business hours and ETS Customer Service has Home Office Workers that gain access through VPN. This will cause them not to be able to provided our customers with any assistance.

John Buchanan

-----Original Message-----
From: ETS Solution Center,
Sent: Thursday, August 30, 2001 9:49 AM
To: Enron Everyone_ET&S_Houston@ENRON
Cc: Rich, Sue
Subject: ETS Corporate Change Control Items


ETS and Corporate Change Control Items

Aug. 30
From 11:00 - 11:30 a.m., the ETS IT team will test the SCADA Frame-Relay Backup to Maitland. Maitland users will lose data and voice connectivity to the GCO network during this maintenance.

Aug. 30
From 7:00 - 8:00 p.m., the HR IT team will upgrade NAHOU-NAHRDW01P. Although this maintenance will result in a total disruption of service to all interfaces into the HRGIM DataWarehouse, no user impact it expected.

Aug. 31
From 10:00 - 11:00 p.m., Enron Network Services will enable layer 2 connections to the Metropolitan Area Network at Ardmore. No impact is expected.

Sept. 1
From 12:00 - 1:00 a.m. (Friday night/Saturday morning) Enron Network Services will add a second gigabit link between core routers ENA-CX1-3405 and ENA-CX2-3405. This maintenance will cause an outage of 30-45 seconds on the core of the Enron network. Any devices communicating to a device on another segment will lose connectivity during this maintenance. Users who are not on the same segment as their servers may experience a disruption of service. This outage will affect access to Notes, Outlook, Phoneline, and access to the Internet.

Sept. 1
From 9:00 a.m. - 12:00 p.m., Telephony services will move the MCI/WorldCom cabinet in 3440. No impact is expected.

Sept. 4
From 3:00 - 5:00 p.m., the Remote Services team will upgrade the CES2 VPN box. This change will result in a total disruption of service for users accessing Enron through the VPN.

Sept. 7
Beginning today, the database for the DSS system will be migrated from GTHOU-SQRPT01P to the ETS Production SAN (GTARD-SQRPT01P). ODBC drivers for Corp users will be pushed out using the login script. Updates to ODBC drivers for EES users will be done manually. The database on GTHOU-SQRPT01P will no longer be available after 9/17.

Sept. 10
From 8:00 - 9:00 a.m., the HR server team will place an eHRonline server into the DMZ for the click-at-home project. No impact is expected.


ETS Solution Center - Houston, at 713-345-4745