If just looking at the crossing, we should be under the $25,000. I
estimated by using 300' x $50/foot. Let me know if you need more info. Larry_Campbell%ENRON@EOTT.COM on 02/27/2001 06:00:24 PM To: Matt_Hughes@Enron.com cc: Scott_Jones@eott.com, Kenny_Maltby@eott.com Subject: Fee Increase, from California Fish and Game Matt, the F&G has increased their permit fees that they charge to access and cross streambeds for pipeline construction projects. The fees only take into account the streambed crossing. to make this as simple as I can, the catagories are : streambed crossing construction costs of less than $25,000 no fee streambed crossing construction costs of $25,000 to $500,000 $618.75 streambed crossing constructoin costs of greater than $500,000 $1390.50 Whats your best guess? The F&G is holding up the issuing of our permit for this activity untill I send them the construction costs numbers and additional fee. Your help will be appreciated.
|