A phase I due diligence was completed for EOTT on two liquids pipeline
segments in the Texas Panhandle and in Northwestern Colorado. The assets are
owned by Equilon Pipeline Company. A copy of the findings have been
submitted to Legal. There were some deficiencies and potential liabilities
discovered as a result of this activity.
Assisted the Roswell team in the preparation and completion of the 6 month
and 12 Title V certification reports for the Roswell C/S. No deficiencies or
non compliance issues were identified for this 12 month period.
Annual certification reports were submitted to the TNRCC for 3 Transwestern
and 8 Northern Natural Gas C/S in west Texas. There wer no deficiencies or
non compliance issues identified for any of the 11 facilities during this 12
month period.
The TNRCC reviewed the emissions testing report for the NNG Plains C/S and
requested modification to the original report submitted. The testing
contractor was contacted and a revised report was submitted to the agency.