You will need this!!

confirming our conversation......reserve emissions for a nom 350KW (gas if
prime - diesel if standby) gen set at each site








Larry Campbell@ENRON
02/14/2001 05:30 PM
To: Arnold L Eisenstein/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT
cc: Earl Chanley/ET&S/Enron@Enron
Subject: Re: loading range of the RB211

Arnold, to be safe Im going to permit at 50-100%. that should be
conservative and allow for minor excursions.....


To: Larry Campbell/ET&S/Enron@ENRON
cc: Earl Chanley/ET&S/Enron@Enron

Subject: Re: loading range of the RB211

normal guarentees are from 50% to 100% load at site rated conditions.

we will probably require 40% for these units and make some mods to the
control system, still determining requirements

Arnold





Larry Campbell@ENRON
02/14/2001 04:30 PM
To: Earl Chanley/ET&S/Enron@Enron, Arnold L
Eisenstein/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT
cc:
Subject: loading range of the RB211

Guys, emissions guarantees are in part calculated upon loading range of the
turbines. In order to get an accurate emissions number for each of the four
locations, would you please provide to me the "loading range" of the turbines
at each of their respective locations?

thanx very much