The state of Texas conducted an air quality inspection of the NNG Seminole
C/S. There were no deficiencies or violations identified at the facilit
during the inspection.

The State of New Mexico Air Quality Bureau conducted an inspection of the
Transwestern Atoka No. 3 C/S. The Agency conducted a record review and did
portable emissions testing of 3 of the 5 emissions units at the facility.
Although fuel use and a natural gas analysis were not available for the units
tested, emissions exceedances for NOx are expected for the 2 White Superiors
at the facility.

The State of New Mexico Air Quality Buureau conducted an inspection of the
Transwestern Atoka No. 2 C/S. The agency conducted a portable emissions
testing of the two turbines and one recip at the facility. Although fuel use
and a natural gas analysis was not available at the facility, all units
tested appeared to be in compliance with the permit limits. The agency
requested sulfur readings from the fuel gas as required under Subpart GG NSPS
for the last twelve months. The Artesia team has contacted Gas Control in
Houston for the for the monthly sulfur values at the facility.