Enron Mail

From:jeff.dasovich@enron.com
To:david.parquet@enron.com, samuel.wehn@enron.com, laird.dyer@enron.com,michael.mcdonald@enron.com, susan.mara@enron.com
Subject:Cal ISO interconnection proc. Amend 39
Cc:
Bcc:
Date:Wed, 11 Apr 2001 03:26:00 -0700 (PDT)

FYI.
----- Forwarded by Jeff Dasovich/NA/Enron on 04/11/2001 10:25 AM -----

Christi L Nicolay@ECT
04/11/2001 09:21 AM

To: Susan J Mara/NA/Enron@ENRON, Alan Comnes/PDX/ECT@ECT, Jeff
Dasovich/NA/Enron@Enron, Steve Walton/HOU/ECT@ECT
cc: James D Steffes/NA/Enron@Enron
Subject: Cal ISO interconnection proc. Amend 39

I reviewed the Cal ISO filings below (in Sue's note) to determine general
consistency with FERC orders on interconnection procedures. Potential issues
are identified below and you all can decide if Enron should protest/intervene
(the West Developers may want to review this too). Since I am not familiar
with the Cal ISO procedures, I cannot determine whether protest is necessary
(for example, PJM, NY, and NEPOOL have certain interconnection policies that
would not be acceptable outside the pool, but that work ok for the pool).
The TOs have also filed Amend. 39 interconnection procedures, but I have not
looked at those to see if they mirror these. Maybe one of the paralegals
could check that. In addition, one of you should review the filing letter
and procedures to make sure that the statements made by Cal ISO are correct.

(Filing letter) The Cal ISO states that these procedures are filed in
response to FERC's orders and that the Cal ISO and Market Participants are
examining policies that will ensure that the ISO Controlled Grid is expanded
to support competitive markets. It also states that it would have liked to
propose complementary changes to its long-term planning and expansion
process, but other priorities have prevented it from doing so.
Discusses the two previously methodologies regarding interconnection
procedures -- "No Grandfathering of Transmission Rights" and "Advance
Congestion Cost Mitigation" (which was apparently rejected last year.
(Filing Letter at 10) -- Cal ISO does not propose a method of sharing upgrade
costs, but states that the procedures do not preclude such a provision. This
is one we have used in other Inter. Agreements: If required by law or if the
Parties mutually agree to allow one or more third parties to use the
Interconnection Facilities or any part thereof (whether by transfer of the
Interconnection Facilities to an RTO or otherwise) and such use decreases the
capacity of the Interconnection Facilities available to TO or the Facility or
otherwise causes any detriment to TO or the Facility or benefits any party
(including TO) other than Generator, or if TO is compensated for the costs of
the Interconnection Facilities (in whole or in part) for any reason,
Generator will be entitled to compensation from TO based upon the pro rata
use of the Interconnection Facilities by TO, all third party users, and
Generator, for the greater of (i) whatever costs Generator incurred in
connection with the Interconnection Facilities, plus interest at the Interest
Rate from the date of Generator's payment of the costs in connection with the
Interconnection Facilities and (ii) the value that TO receives for the
Interconnection Facilities. Notwithstanding the foregoing sentence, the
Parties may use any other mutually agreed upon methodology to determine such
compensation.
3.3 If one or more third parties are to use the Interconnection Facilities in
accordance with Section ___, Generator's obligation to reimburse TO for the
operation and maintenance costs incurred by TO in connection with the
Interconnection Facilities shall be based on the pro rata use of the
Interconnection Facilities by TO, all third parties users, and Generator, or
on some other mutually agreed upon methodology; provided, however, that,
under no circumstances shall Generator's share of TO's operation and
maintenance costs be greater than its pro rata use of the Interconnection
Facilities.
(Procedures) The timelines for submitting applications and responding to
system impact studies (SIS) and facilities study (FS) are fine, per previous
FERC orders (in fact, Cal ISO asks for 60 days to complete the Facilities
Study -- PGE just filed requesting 90 days).
5.7.3.1.1.© I would add "on a non-discriminatory basis" after "unless
otherwise agreed by the ISO, and the Interconnecting PTO"
5.7.4.2 allows the generator to perform its own SIS and FS, subject to review
by the Cal ISO and TO (this is a good provision that has not been adopted by
many utilities).
5.7.4.2.1 -- The SIS will identify adverse impact on "Encumbrances"
(undefined). Someone needs to check this provision since I am not familiar
with this Cal ISO rule.
5.7.4.2.2 -- A New Facility Operator is entitled to amend its Completed
Application once without losing its queue spot. Other utilities allow
amendments as long as the change is not "material", which has only been
defined by the utility and approved by FERC in several cases. This Cal ISO
proposed provision could be problematic to other generators in the queue if
it is not limited to "material", (unless Enron is making the one time
change!) In any event, check with West Developers on this provision.
5.7.4.3 -- This provision requiring a New Facility Operator to execute (or
have filed unsigned at FERC) an Interconnection Agreement within 10 days (if
no upgrades) or within 30 days (if upgrades) can be a problem. Cal ISO does
not file a pro forma Interconnection Agreement in these procedures. If Cal
ISO tenders a poor interconnection agreement draft (which happens all the
time with other utilities), then there is no way that Enron would typically
want to execute it within those time limits. For example, Duke did not file
an pro forma interconnection agreement, but does allow 90 days for
negotiation. In my experience, the negotiation of the interconnection
agreement can take a long time. It would be advisable for the Cal ISO to
file a pro forma at FERC, then you can protest, if necessary, and at least
there will be a fairly decent interconnection agreement to use.
5.7.4.4.1(a) -- The Queuing Milestones appear to be fairly rigid and quick:
require the New Facility Operator to comply with the ISO tariff and the TO
tariff and within 6 months of its Completed Application Date, satisfy all
applicable Data Adequacy Requirements of state and local siting and other
regulatory authorities. I don't know that 6 months is achievable. FERC has
approved milestones in other cases, but most contain language requiring
reasonable movement toward the milestones. For example in Duke ER01-794
Section 41.5: (Transmission Provider may reasonably extend any such milestone
dates in the event of delays not caused by the Generation Interconnection
Customer, such as unforeseen regulatory or construction delays that could not
be remedied by Gen. Int. Customer through the exercise of due diligence, and
may also reasonably extend milestone dates to which the Gen. Int. Customer
has not agreed and which the Gen. Int. Customer has challenged at the
Commission pending a Commission determination as to the reasonableness of
such dates.) In addition, the Cal ISO only allows one extension of 30 days
-- probably not enough.
5.7.4.4.1 (b) -- requires a New Facility License within 15 months after
satisfying the Data Adequacy Requirements.
5.7.5 -- does not provide for transmission credits for "network upgrades"
(upgrades other than the costs of interconnection). The Cal ISO recognized
this exclusion in its filing letter at 11, but thinks that such issues are
appropriately addressed as part of the process to revise the ISO's long-term
grid planning process. Enron has argued and won at FERC for transmission
credits in other utility cases, but I don't know what is appropriate under
Cal ISO system, so please check this carefully.
---------------------- Forwarded by Christi L Nicolay/HOU/ECT on 04/11/2001
08:02 AM ---------------------------


Susan J Mara@ENRON
04/05/2001 03:18 PM
To: Christi L Nicolay/HOU/ECT@ECT
cc:

Subject: RE: FERC FIlings

I complained to the ISO Webmaster and Voila! I guess I was looking in the
wrong spot

Sue Mara
Enron Corp.
Tel: (415) 782-7802
Fax:(415) 782-7854
----- Forwarded by Susan J Mara/NA/Enron on 04/05/2001 01:14 PM -----

WebMaster <WebMaster@caiso.com<
04/05/2001 01:11 PM

To: "Mara, Sue" <smara@enron.com<
cc:
Subject: RE: FERC FIlings

Its under Public Info, FERC Filings and Rulings, Tariff Amendments.
Here's the direct link

http://www2.caiso.com/docs/2001/04/02/200104021630021868.html

-----Original Message-----
From: smara@enron.com [mailto:smara@enron.com]
Sent: Thursday, April 05, 2001 1:05 PM
To: webmaster@caiso.com
Cc: webmaster@caiso.com
Subject: FERC FIlings


I am looking for the ISO's FERC filing that was made on April 2 -- of
Amendment No. 39 on the New Facility Interconnection procedures.