Enron Mail

From:brenda.herod@enron.com
To:michael.eiben@enron.com
Subject:Re: Fuel
Cc:edward.gottlob@enron.com, lisa.csikos@enron.com, daren.farmer@enron.com,mary.smith@enron.com, rita.wynne@enron.com, steve.venturatos@enron.com, pat.clynes@enron.com, edward.gottlob@enron.com
Bcc:edward.gottlob@enron.com, lisa.csikos@enron.com, daren.farmer@enron.com,mary.smith@enron.com, rita.wynne@enron.com, steve.venturatos@enron.com, pat.clynes@enron.com, edward.gottlob@enron.com
Date:Thu, 22 Jun 2000 11:13:00 -0700 (PDT)

Per Mary, Sitara can not handle it either. It can calculate and withhold
volume from the deal as a % for fuel, but not as part of the price. Steve
says this is a nightmare for the Denver office. Can you take the "To Do" to
follow-up on this throughout the systems, and get back with Ed to further
discuss? I'd really appreciate it.




Michael Eiben
06/22/2000 01:09 PM
To: Brenda F Herod/HOU/ECT@ECT
cc: Lisa Csikos/HOU/ECT@ECT, Daren J Farmer/HOU/ECT@ECT, Mary M
Smith/HOU/ECT@ECT, Rita Wynne/HOU/ECT@ECT, Steve Venturatos/HOU/ECT@ECT, Pat
Clynes/Corp/Enron@ENRON, Edward D Gottlob/HOU/ECT@ECT
Subject: Re: Fuel

We need to discuss further. My concern would be that how do we know what %
HPL should be retaining at a compressor or zone to make sure we recoup our
fuel cost ? Also, could allocated fuel cause a contract imbalance? I think
that Pipeline Operations can handle the scheduling of third party fuel
retainage. But, if we retain fuel on ENA transports, then we need to come up
with a plan to nominate this in Marketing Operations to Houston Pipeline.
Currently, this process is not in place.



Enron North America Corp.

From: Brenda F Herod 06/22/2000 12:35 PM


To: Lisa Csikos/HOU/ECT@ECT, Daren J Farmer/HOU/ECT@ECT, Mary M
Smith/HOU/ECT@ECT, Rita Wynne/HOU/ECT@ECT, Steve Venturatos/HOU/ECT@ECT, Pat
Clynes/Corp/Enron@ENRON, Michael Eiben/HOU/ECT@ECT
cc: Edward D Gottlob/HOU/ECT@ECT
Subject: Re: Fuel

What is the answer? Can the systems and processes handle this? Please let
me know ASAP. Thanks.



Edward D Gottlob
06/22/2000 10:57 AM
To: bherod@enron.com
cc:
Subject: Fuel

Brenda,

As you know fuel is a big risk. One of the things we are trying to do is get
the shipper to pay fuel. This would mean we would purchase, transport and
possibly sell gas with a fuel percentage as part of the price. Can the
downstream systems, scheduling etc handle this?