Step # 1 has been completed.
Sherlyn, verify step # 2 tomorrow and call me when completed.

Jackie, verify the nom on Oct 4 & 5. It appears there is still a volume for
meter 6892 until Oct 6.

If there are any questions or issues, contact me at 37649. I am the contact
person while Clem is out (through Friday).
HC
---------------------- Forwarded by Howard B Camp/HOU/ECT on 10/04/2000 01:01
PM ---------------------------


Romeo D'Souza
10/04/2000 12:40 PM
To: Clem Cernosek/HOU/ECT@ECT
cc: Michael Eiben/HOU/ECT@ECT, Howard B Camp/HOU/ECT@ECT
Subject: Re: Tetco/HPL (Enerfin) Meter #986892


Clem,

I have completed setting the confirm = 0 for 986892 and reallocated
all the days. They are all zero now, however 10/4/2000 and 10/5/2000
still have a non-zero BAV, these should get set to 0 by 10/6. Since
allocation will not allocate these days till 10/6 gas date.

r.d




Clem Cernosek
10/03/2000 05:19 PM
To: Donna Consemiu/HOU/ECT@ECT, Romeo D'Souza/HOU/ECT@ECT, Sherlyn
Schumack/HOU/ECT@ECT, Jackie Young/HOU/ECT@ECT
cc: Michael Eiben/HOU/ECT@ECT, Rita Wynne/HOU/ECT@ECT, Pat
Clynes/Corp/Enron@ENRON, Daren J Farmer/HOU/ECT@ECT, Gary A
Hanks/HOU/ECT@ECT, Victor Lamadrid/HOU/ECT@ECT, Howard B Camp/HOU/ECT@ECT
Subject: Tetco/HPL (Enerfin) Meter #986892

Step I.

Romeo: Please do Step 1 today, 10/4/00.

1. Please change the confirmed noms to zero for all contracts that have be
nominated for period 1/1/00 thru 10/31/00 for the above meter.
2. Change the allocation method to "Not Allocatable" effective 1/1/99.
3. Please reallocate the meter for period 1/1/99 thru 10/31/00.
4. Call me after the above tasks have been completed.

Step II.

Sherlyn: Please check the following tommorrow, 10/5/00.

1 Verify with Settlements that the zero BAV adjustment were received for
all Contract Activities at Meter 986892 for period 1/1/99 thru 9/30/00.
2. After verification is complete, please call me.

Step III.

Donna: I will call you tomorrow, 10/5/00 to inform when you can make the
following changes:

1. Change the meter # and DRN # at Facility # 501026. This facility should
be Trade and Nom "YES".
2. Change the meter # and DRN # at Facility # 515136. This facility should
be Trade and Nom "No".
3. After completion, please call me as well as Romeo (x-34544).

Step IV.

Romeo: Upon receiving a call from Donna:

1. Please make the appropriate changes or corrections in POPs System for the
Facility Changes made by Global Facilities Dept. My understanding is that
these changes can not be done automatically.
2. Upon completion, please call me.

Step V.

Jackie:

1. Tomorrow, 10/05 /00, after I am informed that Romeo has made his changes,
I will let you know and you may begin scheduling Meter #0980439 which is the
meter replacing #0986892.
2. After completion, please let me know.

********

Gary:

This could create some problems for Gas Control, because all confirmed
volumes will be zeroed including October, 2000 activities at meter 986892
today (10/4/00). This should correct itself within 24 thru 48 hours at
meter #980439.

Daren:

This could also create some issues for you, but remember, these issues should
clear within 24 to 48 hours.

Victor:

This is just for your information, since this should not create and changes
for you.



IF ANYONE HAS ANY QUESTIONS, PLEASE FEEL FREE TO CALL ME AT X-3665O.

THANKS, CLEM