Mark,
I thought the CA included an LOT term in both the numerator and denominator, which is how I am coding it in the Crystal Reprots application. JD Mark Fisher 05/29/2002 08:30 AM To: Stan Ballard/EWC/Enron@ENRON cc: Hollis Kimbrough/EWC/Enron@ENRON Subject: Availability formulas used These are the approximations (since no manual data was used) used in the tables you were provided. "Enron Availability" ea = (SOT+LOT+WOT+EST)/ST Contractual Availability (EPC) ca=(survey-DT-RT-MT)/(survey-4/(31*24)) Where SOT= System OK time DT= Down Time LOT= Line Out Time WOT= Weather Out time EST= External Stop Time MT= Maintenance time RT= Repair time ST=SOT+DT+LOT+WOT+EST+MT+RT survey= Survey time the 4/(31*24) is an approximation for the prorating of the allowed "4 hours per month" for maintenance time. If you have questions let me know. Mark
|