Jim,
Attached is our report for WTG 79 which answers the questions posed by Eickoff. Please note that we provided more information than we were asked for in anticipation of additional questions from them, yourself and engineering. In the attached report we have provided graphs which cover the previous month (versus the previous week), the production since commissioning (through February), and a fault list. The gaps in the data occur wherever the SCADA system did not record data or it was corrupted in some way. Please note the fault data is particularly susceptible to data integrity problems but it does appear that we had pretty good data recovery during this period. In the graph section we included a graph of Gen rpm/rotor rpm which should yield the gearbox gear ratio (a constant). However, interestingly enough the values fluctuated from time to time which we cannot explain. We will have Trent Mesa WTG #30 for you tomorrow morning. Best Regards, Hollis
|