Enron Mail

From:chris.germany@enron.com
To:ingrid.immer@williams.com
Subject:Hey
Cc:
Bcc:
Date:Wed, 1 Mar 2000 06:52:00 -0800 (PST)

Here is what Vickie told me about capacity on your pipeline after you
eliminate segmenting.

Example #1

Assumtion: PECO has 10,000 dt/day of telescoped capacity with a primary
delivery point of PECO in Z6.
What will Enron and PECO be able to schedule Iff PECO releases 10,000 dt/day
of St 65 to PECO citygate under the following scenarios;

PECO schedules gas from St 30 to WSS, and Enron schedules gas from
Tetco/Ragley to Z6?

PECO schedules gas from St 30 to St 65, and Enron schedules gas from St 65 to
Z6?


Assumtion #2: PECO released Enron 10,000 dt/day of telescoped capacity.

Enron schedules gas from St 30 to WSS, and from Tetco/Ragley to Z6?