We wouldn't be a generation only control area. Our load is Valley Electric.
My bigger worry is how do we meet our generation requirement if we sell off LV Cogen. Also, when the RTO forms, all control areas will be consolidated, at least if their transmission is in RTO West. To: Mary Hain/HOU/ECT@ECT cc: Subject: West control area Can you and Sean Crandall call me about this? There have been a variety of problems with the full use of the sink provision based on FERC's Entergy order. Also, ComEd and TVA have precluded us from sinking at the generation only control area and FERC hotline has said this can be done without a FERC filing (or at least we would have to pursue it in a complaint--we don't want that result in a FERC order.) In addition, while you were on vacation, Nevada Power had the problem with Salt River Project. I don't know the status of that. I am in a room reviewing etrans tariff, so page me if you want to talk about it. 800-778-8365. Thanks.
|