On 12/17/00, Duke filed interconnection procedures at FERC. It did not file
a pro forma Interconnection Agreement. The procedures are generally fine and include: Posting of a queue (should be on the OASIS now) Negotiation of milestones List of Studies performed within the last 2 years will be on OASIS and available (with the customer name redacted) A new request (new queue spot) will be required for: any increase in the rated capacity of generating facilities or any other significant changes including, (1) a site change that impacts the flow of power on Duke's system, (2) change in interconnection point of < 5 miles or 25% of the length of the line to which the generating facility is connected; or (3) delay of commercial ops date of more than 6 months. FERC has not approved this filing yet.
|