I have looked on APS' OASIS for the substations you mentioned. The only one
listed as a receipt point was Moenkopi. Below is a list of the other receipt
points available. I'll be out next week but if you need help looking to see
if transmission capacity is available Diana, Paul, or Cara may be able to
help you.

Cholla 345
Desert Basin
Four Corners 230
Four Corners 345
GIla 69
Knox 230
Kyrene 230
Marketplace
MCC5
Mead 230
Mead 500
NavaJo 500
North GIla 500
PNPKAPS 230
Saguaro 500
San Luis 34
West Wing 500
Yucca 69




Javier Li@EES
02/28/2001 01:48 PM
To: Mary Hain/HOU/ECT@ECT
cc: Marc Pana/HOU/EES@EES
Subject: Interconnection in Arizona

Mary, I am working with Jeff Golden and Marc Pana in EES Corporate
Development. Marc asked me to send you a list of potential substations for
interconnection of mobile generation in blocks of 25 MW to 50 MW. Here is a
tentative list. Please feel free to suggest any other location you think is
suitable for trading power in Palo Verde (either directly or with power
displacement). Thanks for your attention.

Javier.
x. 34599

Tapco (has abandoned plant?)
Ash Fork
Williams
Parks
Winona
Leupp
Round Valley
Cataract Creek
Moenkopi
Sedona
Goodard
Kirkland