Rod, here is my input on the 2000 Goals and Objectives. My numbering will
correspond to the list of goals and objectives which accompanied your e-mail. 1. Completed. Final certificate was gotten in Feb. 2000 and the west leg construction was completed and in service around 10/1. 2. Partially completed. PD received on Phase 5 on 11/21 but the EIS is not expected til 1/01. 3. No input. 4. No input. 5. Completed. 6. As you know, CitrusNet was not completed. We have developed a good structure for the transaction being considered a sale and we have developed the necessary contract documents to accomplish the deal but at present we have no takers. 7. No comments. 8. I think this was intended to be the MOPS sale which I believe has been moved to next year. 9. No comment. 10. Efforts were made with a couple of potential buyers to work out a deal but nothing definitive was accomplished. 11. A lot of work was done in connection with Project Cristobal but nothing was finalized with potential partners. 12. No comment.
|