Subject:Entergy - Desoto County Project / Potential Change in FP&L
Cc:
Bcc:
Date:Tue, 25 Jul 2000 00:30:00 -0700 (PDT)

Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
X-From: Rockford Meyer
X-To: Stanley Horton
X-cc:
X-bcc:
X-Folder: \Stanley_Horton_1\Notes Folders\All documents
X-Origin: HORTON-S
X-FileName: shorton.nsf

fyi


---------------------- Forwarded by Rockford Meyer/FGT/Enron on 07/25/2000
07:31 AM ---------------------------
From: Jack Boatman on 07/24/2000 04:19 PM
To: Robert Hayes/FGT/Enron@ENRON, Rockford Meyer/FGT/Enron@ENRON, Robert
Kilmer/FGT/Enron@ENRON
cc:

Subject: Entergy - Desoto County Project / Potential Change in FP&L "Strategy"

Per discussions with Entergy today regarding the Desoto County peaking
project:
- Entergy has an internal meeting planned later this week to decide if they
want to continue with the project
- The Desoto site is one of the sites which IPS did the groundwork for, as
far as permitting, etc.

* Entergy has a meeting scheduled with FPL to discuss a "tolling
arrangement, whereby FP&L would provide gas deliveries to obtain a
portion of the power output ------ Note: I said this would be a major
change in FP&L's business approach and Entergy indicated FP&L appears
to be changing their thinking regarding merchant power plants and that
FP&L may announce a new "position" on merchant plants in the next few weeks