Enron Mail

From:craig.breslau@enron.com
To:dan.hyvl@enron.com
Subject:ormet
Cc:
Bcc:
Date:Tue, 21 Nov 2000 06:40:00 -0800 (PST)

1. Change the bold in 1. to "for any reason other than an event of Force
Majeure having the effect of rendering customer unable to accept any volumes
at the primary delivery point during the continuation of such event of force
majeure.

2. in 1 say that demand charges shall not exceed .055. Also put in there
that we will provide customer with a copy of Koch's transportation invoice to
verify what we are charged for deficient volumes.


3. Add a sentence at the end of no.1 that says that "Provided that prioir to
Company's incurring those incremental gas transportation and/or gas supply
costs, customer agrees to pay the incremental amount. " (they want us to
notify them first and have them agree before we schedule the gas to them)

4. On the contract, in the definition of Force Majeure they want to add
"for any reason including but not limited to operational or economic reasons"