Per our Monday meeting, the time line for completion of the "Phase I"
forecasting project (Hourly System Load & Next Day Load) is as follows: Aug. 15 - Sept. 15 (Data Collection) Sept. 15 - Oct. 15 (Modeling) Oct. 15 - Nov. 15 (System Development and Testing) If any questions arise between now and the end of August, contact Barbara Dillard, but as of Sept. 1, I will be the Chicago lead for this and other forecasting projects and will be available to handle any questions or issues. Best regards, Mark Mixon
|