TGP's DracutExpansion Receives FERC Approval

Tennessee Gas Pipeline has accepted the FERC's certificate
authorizing construction of the Dracut Expansion project. The $35
million project will replace 12 miles of existing 16-inch natural gas
pipeline with a 24-inch pipeline from Dracutto Burlington,
Massachusetts, primarily using existing rights-of-way. The project
will increase takeaway capacity from the Dracutinterconnect by an
additional 200,000 MMBtu per day. Once the project is in service,
the total capacity from Dracutwill increase to more than 600,000
MMBtu per day. The project is scheduled to be available for service
next fall. Tennesseeinitiated the growth by completing the Eastern
Express 2000 project in January, 2000 and placed the Londonderry
pipeline in service in September, 2001.