Please find below the weekly project status update for GTV and the attached file for the updated project timelines. Changes are underlined.

GTV status meeting attendees: Zhiyong Wei, Jeremy Wong, Nayan Dattani, Bill Fortney, Karima Husain, Thu Dang, Chuck Ames, Geoff Storey, Jay Krish, Russ Severson, George Grant, Mike Swaim.

Accomplishments:
? Incorporating physical deal positions in TDS:
o Changes for the view aggregation have been completed.
o Expandable Total in Cash Position has been completed.
? Single point of deal entry for term deals:
o Released to production.
? Gas Daily deals:
o Released to production.
? Live feeds for Gas Daily/intra-month curves:
o Released to production.
? Saving different views in TDS:
o Completed.
? Capability for desk roll-ups on an ad hoc basis (phase 2, on hold since 7/9/01):
o New process for roll-up aggregators has been completed.
? Option Grid (phase 2):
o Released to production.
? Gas Daily options (phase 2):
o Released to production.
? Basis Options (phase 2):
o Development of deal entry type for Basis Options has been completed in TAGG.
o Development of loading correlation curves has been completed.
o Changes to the Translator have been completed.
? Transport Deal Capture & Valuation (phase 2):
o Creation of new deal entry type & database changes has been completed.
o Changes to the Translator have been completed.
? Add more information to the drill-down deal details.
o Development has been completed.
? New Flexible Deal Viewer.
o Database schema design has been completed.

Plans for the week ending 08/03/01:
? Continue User acceptance test of physical deal positions in TDS (Phase I items).
? Continue IT development of Phase II issues.
o Change PortCalc to value basis options.
o Option reports (PL reports).
? Add more information to the drill-down deal details.
o User Acceptance Testing.
? New Flexible Deal Viewer.
o Continue GUI development.
o Continue development of Query Engine.
o Start working on loading data and related items.

Issues:
? None.

Notes
? Since Calgary office has not yet implemented the new GDI calc, there was a double counting issue with Canadian Gas Daily books last Friday, July 27. The IT team has been working closely with Calgary office to fix the problem as soon as possible.
? In the last couple of weeks, a developer took a week and half off due to a family emergency and another developer took paternity leave for a week, which affected our project delivery timelines.




Thanks

Zhiyong