Please find below the weekly project status update of GTV and the attached file for the updated project time lines.

GTV status meeting attendees: Thu Dang, Nayan Dattani, Bill Fortney, Jeff Gossett, George Grant, Brad Jones, Narasim Kasaru, Jay Krish, Francis Lim, Russ Severson, Geoff Storey, Michael Swaim, Zhiyong Wei, Jeremy Wong.

Accomplishments:
? GTV2 Phase 1 items
o Released to production.
? Saving different views in TDS:
o Released to production.
? Capability for desk roll-ups on an ad hoc basis (phase 2, on hold since 7/9/01):
o New process for roll-up aggregators has been completed.
? Option Grid (phase 2):
o Released to production.
? Gas Daily options (phase 2):
o Released to production.
? Basis Options (phase 2):
o Development of deal entry type for Basis Options has been completed in TAGG.
o Development of loading correlation curves has been completed.
o Changes to the Translator have been completed.
o Development of Basis Options valuation has been completed.
? Transport Deal Capture & Valuation (phase 2):
o Creation of new deal entry type & database changes has been completed.
o Changes to the Translator have been completed.
? Add more information to the drill-down deal details.
o Released to production.
? New Flexible Deal Viewer.
o Database schema design completed.
o Initial Load of active Deals from Sitara completed.
o TIBCO work completed.
o Units of Measure conversions completed.
o Update of active deals from Sitara completed.
o Development of Query Engine completed.
o Development of Delphi feed to Excel completed.
o Schema mapping completed.
o Initial loading of active deals from TAGG completed.
o 3 new requests (from last Wednesday's demo) for Update Server completed.
o Complete Development of Excel VB.
o Complete remaining new request for Update Server (SIC codes).
o Complete development of update of active deals from TAGG.

Plans for the week ending 09/14/01:
? Continue IT development of Phase II issues.
o Complete Option reports (PL reports).
o Complete integration test of Basis Option valuation.
o Begin change to Portcalc to value Transport deals.
? New Flexible Deal Viewer.
o Complete user acceptance testing.
? Investigate efforts needed to implement TDS for Calgary office.
? Investigate ways of distinguishing deal changes and UNIFY volume feedback.
? Investigate ways of improving EOL bridging to Sitara and TAGG for term physical deals.

Issues:
? None.

Notes
? Canada still needs to test Y-Calc.
? Jeff Gossett is looking into possibly adding more requirements for Option Reports.



Thanks

Zhiyong