Enron Mail

From:kay.mann@enron.com
To:matthew.gockerman@enron.com
Subject:Electrobolt S&S Scope
Cc:
Bcc:
Date:Mon, 28 Aug 2000 03:59:00 -0700 (PDT)

Hi Matt,

ENA is selling some of the LM6000's to ESA. Will you be the ENA Tax Man on
the deal?

Thanks,

Kay
---------------------- Forwarded by Kay Mann/Corp/Enron on 08/28/2000 10:58
AM ---------------------------


Kevin Joyce
08/25/2000 09:51 AM
To: Kay Mann/Corp/Enron@Enron
cc: Roseann Engeldorf/Corp/Enron@ENRON, Lisa Bills/Corp/Enron@ENRON, Brett R
Wiggs/SA/Enron@Enron, Ben Jacoby/HOU/ECT@ECT, John R Ayres/NA/Enron@Enron,
Kent Castleman/NA/Enron@Enron, Mary Cilia/NA/Enron@Enron, Mike
Morrison/NA/Enron@Enron, Chris Booth/NA/Enron@Enron

Subject: Electrobolt S&S Scope

Kay,
Attached is the LM 6000 and options scope that ESA has prepared, that will
be input to our MOU. It does not reflect the scope of equipment that will be
procured from ABB yet; this should be forthcoming. Also below is the current
cost estimate of the machines with their S&S options and the ABB scope.
Please let us know what other information regarding scope that you might
need.

Thanks,
Kevin
---------------------- Forwarded by Kevin Joyce/Corp/Enron on 08/25/2000
09:26 AM ---------------------------
From: John R Ayres on 08/24/2000 01:35 PM
To: Chris Booth/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT
cc: Brett R Wiggs/SA/Enron@Enron, Kevin Joyce/Corp/Enron@Enron, Glauco
Palhoto/SA/Enron@Enron, Gerald L Gobbi/NA/Enron@Enron

Subject: Total Electrobolt S&S Scope

Chris, attached is the total scope to S&S. From this list you should be able
to make your change order to S&S base on purchased quantities versus required
quantities. I have provided you the required quantities.
I provided you a column for the delta cost to S&S. When you are finished,
please complete the spreadsheet for all of our records. I do not know how we
are to add cost for storage either.
Thanks,
John



From: John R Ayres on 08/23/2000 12:38 PM
To: Kevin Joyce/Corp/Enron@Enron
cc: Brett R Wiggs/SA/Enron@Enron

Subject: S&S (GE) Scope of Supply Cost

Here are the total cost for the S&S scope of supply for the Electrobolt
Project. I have not included any ENA burdens or storage cost. These cost
are from purchase order with ENA to S&S.


EIGHT MACHINES EACH
The total cost of the LM 6000's, sprint package, water injection
skid = $112,855,600 or $14,106,950 each
The total cost of options (chillers stacks, cooling tower, mod. buildings,
etc. = 13,309,400 or 1,663,675 each

Totals = $
126,165,000 or $15,770,625 each

The transformers from ABB in Brazil should cost $3,200,000. total in Brazil
without shipping to the site.

Hope this helps you with the WLB bucket.