Al,
If the transformer contract will be assigned later to a wholly owned sub of E-Next (aka the project company) it would seem that the Transfer Date should probably be redefined to reference an assignment to an unaffiliated company. Same thought on the GE override. This is because the override will still be in effect if E-Next owns the equity in the assignee. Kay Alan Larsen@ECT 01/16/2001 01:20 PM To: Sheila Tweed/HOU/ECT@ECT cc: Kay Mann/Corp/Enron@Enron, Ed B Hearn III/HOU/ECT@ECT Subject: ABB Override Letter Here is the revised, and final form, of the ABB override letter for use in conjunction with the FVP breakout contract for FVP.
|