Enron Mail

From:kay.mann@enron.com
To:nwodka@bracepatt.com
Subject:Rocky Mount Meeting Setp 22, 2000
Cc:
Bcc:
Date:Mon, 25 Sep 2000 03:55:00 -0700 (PDT)

---------------------- Forwarded by Kay Mann/Corp/Enron on 09/25/2000 10:55
AM ---------------------------


Reagan Rorschach
09/25/2000 09:43 AM
To: Jeffrey Keenan/HOU/ECT@ECT, John Moore/Corp/Enron@Enron, Ben
Jacoby/HOU/ECT@ECT, Heather Kroll/HOU/ECT@ECT, Kay Mann/Corp/Enron@Enron,
Ozzie Pagan/HOU/ECT@ECT, Karen E Carter/NA/Enron@Enron, Rebecca
Walker/NA/Enron@Enron
cc:

Subject: Rocky Mount Meeting Setp 22, 2000

Meetings with Rocky Mount, Edgecombe County, Appian Consulting Engineers
(local engineering/permitting/landuse consulting firm) resulted in the
following action items:

Edgecombe County
Complete rezoning application
Current landowner needs to sign the application. Ken Raber from
Electrocities will cooperate.
$25 filing fee
Plot plan and meets and bounds are necessary deliverables to the county,
however can lag behind application
Should do entire site (i.e. finalize additional land requirements via Hessler
noise study due this week)
County building permit (visit with Stuart Bass this week to finalize
submittal requirements)
County planning commission meets October 16 and board of county commissioners
meets November 6. Stuart Bass feels that meeting schedules could be
accelerated to accommodate faster rezoning process.
Submit erosion and sedimentation control plan to the state and copy to the
county
Confirm in writing with county list of non-intrusive construction activities
that may be initiated in the interim

City of Rocky Mount
Finalize land needs and Bill Sherk will move forward to secure option
Rocky Mount annexation should be initiated before improvements. This will
help Rocky Mount with regard to local volunteer fire department district
"payment-in-kind" issue.
Finalize water and wastewater needs and commercial operation date with city
(Paul Blount) to coordinate water supply availability
Get water analyses from Betz and subsequent EE&CC help characterizing
expected discharge water quality and flow rate from facility.
Get water/wastewater rate sheet from Paul Blount
Coordinate/file encroachment filing for wastewater line construction in NC
DOT's right-of-way. City will file concurrently for construction of water
line.
Investigate the Tarpamlico (sp?) Ripirian Buffer Regulations
Talk with Bill to understand how Gateway Partnerhip works--funding source,
authority, etc.


North Carolina DOT
Get with Bobby Lewis regarding driveways, curb-cuts, etc.
File for wastewater line encroachment in NC DOT right-of-way


Gateway Partnership (business development entity)
Make friends with Oppie Jorday
Begin to negotiate the tax deal after understanding extent of Gateway
authority, money, and operations

Appian Consulting Engineering (Bobby Joiner)
Get a professional services agreement started
Get rate sheet and T&M numbers from Appian
Give notice to proceed with creation of the erosion and sedimentation control
plan
Give notice to proceed with regard to creation of local/county/state watch
list.