1. Section 6.3.1 (b)--How will lien releases work? By unit or by project?
2. Section 6.4--Delivery Failure--if Purchaser fails to make a site
available for delivery in accordance with the 14 day advanced notice
procedure, don't provide highway access or we change the site after 4 month
advanced notice; Purchaser Acceptance Failure--foundations in accordance with
the specs (if in Purchaser scope) are not available for installation of the
units within __ days of delivery of all the major components to site;
purchaser fails to construct any of its BOP scope to specs within two months
of delivery of all the major components to site. Should be a 5 day notice
period of a Purchaser Default.
3. Section 6.4--Needs to say that payments are applicable to purchase price
and that payments are subject to refund by FCE based on results of Acceptance
Test.
4. 6.7.2--Should we set up a defined term for purchaser. Need to be able to
change.
5. Section 7--I don't know where you want to insert but accounting said that
if our Purchase Order was contingent upon full acceptance and assignment to
RTO unless waived by ENA, we wouldn't have an issue.