Being as the below Sections 10.3.2 (e) and (g) were negotiated for a full
Power Island supply with testing requirements very different from a GTG purchase contract's usual testing requirements, which aslo resulted in the agreement to expand the definition of the Commissioning Period to include all of the "Acceptanc Tests", I do not think that the below sections should be addressed or included in the World Hunger discussions. The preceding was GE's arguement for their change in the first place. There is a world of difference between a 30 day commissioning period for a simple cycle unit and 26 weeks for a power island like we have for Arcos. Apples and oranges applies here. stephen.swift@ps.ge.com 03/13/2001 04:28 PM To: Sheila.Tweed@enron.com, Bill.Williams@enron.com, Dean.Russell@enron.com, Ben.Jacoby@enron.com, Ed.B.Hearn.III@enron.com, Kay.Mann@enron.com, Roseann.Engeldorf@enron.com, Lisa.Bills@enron.com, Brian.D.Barto@enron.com, Scott.Dieball@enron.com, pthompson@andrews-kurth.com, michael.barnas@ps.ge.com, kent.shoemaker@ae.ge.com, John.G.Rigby@enron.com, Dale.Rasmussen@enron.com, Bob.Carter@enron.com, Stuart.Zisman@enron.com cc: Subject: RE: Revised GE Conference Call Attached is GE's suggestion for inclusion into Section 7.1 of the Contract. This clause lays out the timing for any changes without impacting ship dates. ------------------------------------------------ Also below are the revisions that are under discussion for the Arcos contract for Sections 10.3.2 (e) and (g). We can use these as a starting point for these clauses. 10.3.2 (e) Purchaser makes reasonable efforts to provide the necessary time, access and operating loads for Seller and Purchaser to commission and check out the Power Island during the Commissioning Period. Seller's time and load requirement shall not be to the exclusion of the needs of other Station equipment being commissioned. Purchaser shall coordinate the most advantageous utilization of time. In the event Purchaser does not provide reasonable time, access and operating loads during the Commissioning Period, Seller will be entitled to an appropriate adjustment in the cost of additional TD of I (to the extent the allotted manweeks per Appendix ____ are exceeded) and adjustment to the Commissioning Period pursuant to Article ____ of this Contract; (g) In the event Seller fails to use its reasonable efforts to minimize time to make corrections, adjustments or repairs to the deficiently performing Unit during the Commissioning Period, Purchaser shall have the right to reduce the Commissioning Period by the same time period that the Seller has not used reasonable efforts to minimize time to make corrections, adjustments or repairs to the deficiently performing Unit; --------------------------------------------- Talk to y'all tomorrow, Steve Swift - Section 7-1.doc
|