Attached are files incorporating suggested revisions for the change order to
Contract 24-LM6K-2-99 for the purchase of a generator step-up transformer for the Pleasanton Project. In lieu of the Exhibit A of the draft you sent out, I have substituted Exhibit A, the GE proposal dated October 9, 2000. I have substituted Exhibit B, GE's standard specifications for generator step-up transformers, for the EE&CC specifications in the earlier draft. GE's proposal is quoted on the basis of their standard GSU transformer specification. I have this only in hard copy and have a call into GE to verify this is the applicable standard and whether it is available in electronic form. I will give you a copy, Dale. The two additional documents were transmitted along with GE's proposal and I have referenced them in Part I, Paragraph 2.
|