---------------------- Forwarded by Kay Mann/Corp/Enron on 11/09/2000 09:06
AM ---------------------------


Christi L Nicolay@ECT
11/07/2000 01:19 PM
To: Ozzie Pagan/HOU/ECT@ECT
cc: Heather Kroll/HOU/ECT@ECT, Bob Carter/HOU/ECT@ECT, Barbara N
Gray/HOU/ECT@ECT, Lloyd Will/HOU/ECT@ECT, Mitch Robinson/Corp/Enron@Enron,
Patrick Hanse/HOU/ECT@ECT, Ben Jacoby/HOU/ECT@ECT, Barton Clark/HOU/ECT@ECT,
Kay Mann/Corp/Enron@Enron, Larry Soderquist/HOU/ECT@ECT, Bill
Rust/HOU/ECT@ECT, James D Steffes/NA/Enron@Enron, Richard
Shapiro/NA/Enron@Enron, Sarah Novosel/Corp/Enron@ENRON, Joe
Hartsoe/Corp/Enron@ENRON, Donna Fulton/Corp/Enron@ENRON, Mary
Hain/HOU/ECT@ECT

Subject: Re: VEPCO files Interconnection Proc. at FERC

FYI. The VEPCO attorney said that currently VEPCO is taking about 60 days
each for the System Impact Study and the Facilities Study. Because of the
increase in study requests, VEPCO is filing for 90 days for Fac. Studies,
below.





From: Christi L Nicolay 11/06/2000 02:29 PM


To: Ozzie Pagan/HOU/ECT@ECT, Heather Kroll/HOU/ECT@ECT, Bob
Carter/HOU/ECT@ECT, Barbara N Gray/HOU/ECT@ECT, Lloyd Will/HOU/ECT@ECT, Mitch
Robinson/Corp/Enron@Enron, Patrick Hanse/HOU/ECT@ECT, Ben Jacoby/HOU/ECT@ECT,
Barton Clark/HOU/ECT@ECT, Kay Mann/Corp/Enron@Enron, Larry
Soderquist/HOU/ECT@ECT, Bill Rust/HOU/ECT@ECT, James D
Steffes/NA/Enron@Enron, Richard Shapiro/NA/Enron@Enron, Sarah
Novosel/Corp/Enron@ENRON, Joe Hartsoe/Corp/Enron@ENRON, Donna
Fulton/Corp/Enron@ENRON, Mary Hain/HOU/ECT@ECT
cc:

Subject: VEPCO files Interconnection Proc. at FERC

On 10/27/00, VEPCO filed interconnection procedures at FERC (Docket No.
ER01-247)(Protests due 11/17/00). These largely mirror CP&L's
interconnection procedures that were recently approved by FERC. Therefore, I
do not think that Enron should protest or intervene.

Customer is required to pay for the cost of a new system impact/facilities
study if the study information/interconnection/upgrade costs change due to a
customer higher in the queue losing its queue spot.
System impact studies should take 60 days or less. Facilities studies should
take 90 days or less.