Enron Mail |
I'm attaching a revised draft of the option to purchase the land for the
VEPCO deal. I've limited it to the land in Edgecombe County, changed the initial period to 90 days (with 3 x 90 day renewals). The price is changed to $137,600, as have the option payments ($3500 for each 90 day period). Is there anything else which needs to be changed? FYI, I've left a message for Dutch Bumgarnder, VEPCO's lawyer, concerning the interconnection agreement, and who is doing what. Thanks, Kay
|