Enron Mail |
In light of the offsite UBS meeting this morning, today's test will be move=
d from 12:00 to 2:00pm. =20 We will use the same global data already setup from Friday/ Tuesday. Hence= , the deal entry phase can start at 2:00pm. An updated scheduled is attached. =20 Regan Smith=20 Energy Operations Systems=20 Enron Net Works=20 713-853-9291 (wk); 281-850-7551 (cell)=20 -----Original Message----- From: Smith, Regan M.=20 Sent: Tuesday, January 22, 2002 6:17 PM To: Allen, Thresa A.; Anderson, Bridgette; Anderson, Diane; Aucoin, Evelyn;= Baker, Natalie; Baxter, Bryce; Bentley, Corry; Bowen, Bob; Brackett, Debbi= e R.; Campos, Anthony; Campos, Sylvia A.; Dahlke, Andrea; Dawes, Cheryl; De= nny, Jennifer; Denton, Rhonda L.; Dupuy, Mark; Elledge, Susan; Engel, Tom; = Evans, Casey; Garcia, Clarissa; Gillis, Brian; Hare, Bill D.; Hayden, Frank= ; Heal, Kevin; Hunter, Larry Joe; Huntley, Kelley; Jaquet, Tammy; Kenne, Da= wn C.; Lozano, Melba; Mcginnis, Stephanie; McLaughlin Jr., Errol; Meredith,= Kevin; Murphy, Melissa; Price, Wade R.; Reeves, Kathy; Robinson, Rhonda; R= odriguez, Bernice; Schield, Elaine; Schrab, Mark L.; Seib, Dianne; Severson= , Russ; Spears, Christopher; Stevens, Mechelle; Sullivan, Patti; Sweitzer, = Tara; Theriot, Kim S.; Vander velde, Nikole; Wallumrod, Ellen; Winfree, O'N= eal D.; Wynne, Rita; Bharathi, Jaikishore; Brewer, Charles; Chitradurga, Su= ndar; Cinelli, Steve; Elwood, Richard; Fortney, Bill; Franks, Shawn; Greig,= Iain; Henry, Jane Hilburn; Hunter, Wade; Johnson, Jeff; Lim, Francis S.; M= artinez, Bob; McKeel, Richard; Nolte, Ron; Pena, Matt; Poston, David; Powel= l, John D.; Ramesh, Ganapathy; Rao, Ramesh; Saleem, Aftab; Sanvido, Terry; = Schmidt, Mark; Schomer, Chris; Smith, Regan M.; Stock, Steve; Clark, Cynthi= a; Boudreaux, Lori Subject: Status report of integration testing from Tuesday, Jan. 22nd=20 Status report of integration testing from Tuesday, Jan. 22nd=20 (completion of subset of Gas/ Power scenarios to test that all platform= components are setup) =20 We've completed the remainder of test scripts, including transmitting invoi= ces to SAP successfully! =20 And all reported testing issues are resolved (need confirmation by a few us= ers). Thanks to all involved! =20 It was very productive as 16 issues (8 from Unify) were identified and reso= lved (attached). A spreadsheet is attached of the outstanding/ resolved issues If any test= ing issues are missing and not reflected, please email Terry Sanvido or mys= elf to assist with tracking and resolution. =20 The importance of Wednesday's test below is: =20 (1) to test after all estate data removal is done; as if testing a Net= co 'go-live' (2) to test all (15+) transaction scenarios 'end to end' test. =20 A reminder of Aftab's email requesting your assistance is attached. =20 Schedule for Wednesday 01/23 (complete set of scenarios to be tested) (1) By 11:00am - all IT systems to have deleted any estate data & backups c= ompleted (2) 11:00am - Global to repush any setup data if needed (3) 12:00pm - any global data setup by users (we may=20 (4) 1:00pm - 5:00pm User integration test of all test scenarios. The goal = is to test 'end to end' to ensure the all issues are resolved, and data rem= oval and resetup is valid. - Bridgeline open to discuss issues (800-711-8000; code #3454709) =20 =20 We appreciate your support as we work towards setting up the NETCO! =20 Regan Smith=20 Energy Operations Systems=20 Enron Net Works=20 713-853-9291 (wk); 281-850-7551 (cell)=20
|