This spreadsheet corrects the graph in the previously submitted spreadsheet,
removing the last two data points. Data is only through June 2000, and the graph incorrectly also showed the average numbers as if they were numbers for July and August 2000. ---------------------- Forwarded by Arvel Martin/HOU/ECT on 07/25/2000 04:47 PM --------------------------- Arvel Martin 07/25/2000 03:43 PM To: Gerald Nemec/HOU/ECT@ECT cc: Joan M Quick/HOU/ECT@ECT Subject: Crescendo Pressure Data The attached is a monthy table w/ a summary of line pressures and production. Take a look and see if this is what you need. Notice the sheet called "Summary by month and average", especially the last few columns with averages calculated. Remember, most of the Entrada Production went off-line beginning in 1998, with final production in August 99. Call me @ 3-1888 if we need to discuss. Arvel
|