The Wildhorse Operating Team met yesterday (Thursday 08/10) and I was
informed this morning that Wildhorse has decided to present us a formal proposal to gather Crescendo's Entrada gas from San Arroyo. Wildhorse told me to expect the proposal by Friday 08/18; I'll continue to monitor next week to ensure they do not delay any further. The nature of the project would be similar to what Wildhorse discussed with NG Resources in the past...Wildhorse will construct certain pipeline segments in order to isolate a seperate low Btu gathering line from San Arroyo to Crescendo's proposed plant location at Badger Wash. Obviously, when Ken (or myself) receives the proposal, a group meeting would be very beneficial as I'm sure there will be numerous questions/issues for us to contemplate.....gathering capacity, structure, contract issues, plant issues, etc. Talk to everyone at the Tues. meeting. Dan
|