Attached is the Tejas Kingsville Interconnect Agreement with the most recent
changes.

Note: The previous version of this Agreement had a cap of $27,000.00 for
costs incurred by TGPL (& reimbursed by HPL) for the construction of the TGPL
Facilities and the TGPL Operated Facilities. In this version HPL is
constructing the TGPL Operated Facilities therefore the only costs incurred
by TGPL will be for the TGPL Facilities (i.e. the $27,000.00 figure is no
longer applicable). The document currently limits reimbursement to
reasonable costs. If you feel a hard cap on expenses for the TGPL Facilities
(the tap, riser and valve) is required, I need a dollar amount to add that
provision to the document.



Thanks,

Eric Gillaspie
713-345-7667