Greg, I thought that was for the Rio Nogales project. The Brazos Valley
interconnect has no specific provisions for assignment to Pinnacle. Greg Brazaitis 05/11/2001 11:06 AM To: Gerald Nemec/HOU/ECT@ECT cc: Subject: Re: Brazos Valley Gerald, We have an executed Corporate Guarantee from Constellation for the work to be done at the Interconnect. We estimate the cost to install at $100K. The guarantee is for $300K. Constellation will be responsible for the costs even if the Interconnect is assigned, as is permitted by the Interconnect Agreement, to Pinnacle (PNG Utility). Greg
|