Enron Mail |
---------------------- Forwarded by Kevin M Presto/HOU/ECT on 05/21/2001 02:49 PM --------------------------- From: Kristin Walsh/ENRON@enronXgate on 05/21/2001 02:19 PM To: Kevin M Presto/HOU/ECT@ECT cc: Lloyd Will/HOU/ECT@ECT, Kelly Holman/ENRON@enronXgate Subject: New Gen Hays Plant; ANP (International Power) San Marcos, Texas; ERCOT ? 4 units (instead of 6) each 275MW; Total MW = 1,100 ? Unit One - tested - had first fire and is currently being scheduled for 100 hour test - sometime mid to late June ? Unit Two - testing tomorrow - first fire ? Unit Three and Unit Four- testing completed by September, October ? Plant completion - October or November Comments from Plant Operator: ? "Project is way, way behind schedule and is going very slow" ? Unit 1 and Unit 2 - "We are trying to get them (Unit 1 & Unit 2) commercial by the end July and keep them up through September. After September we intend on going back to testing Units 3 & 4, with total plant completion date of October/November."
|