We need the hourly option to allow for non-GTC sources, but we will deliver into-GTC border hourly.

-----Original Message-----
From: Braddock, Billy
Sent: Tuesday, October 09, 2001 12:55 PM
To: Presto, Kevin M.
Subject: RE: TEA - into MEAG

TEA will let us go hourly 5 times per month and change the source if we go hourly, as long as the source remains a unit on the Ga-ITS. However, he doesn't want a full 50MW block in the June-Sept period, just 40MW. The 40MW is actually already at the high end of his range (needs 30-40MW for June-Sep).

-----Original Message-----
From: Presto, Kevin M.
Sent: Monday, October 08, 2001 3:04 PM
To: Braddock, Billy
Subject: RE: TEA - into MEAG

Will he let us go hourly at least 5 times per month and change the source if we go hourly. This essentially would require they provide parking and lending for up 20 MW in the Cal and 40 MW in the June-Sept. Can we at least get a 50 MW block in the June-Sept period?


-----Original Message-----
From: Braddock, Billy
Sent: Monday, October 08, 2001 2:44 PM
To: Presto, Kevin M.
Subject: RE: TEA - into MEAG

An offer from any Scherer unit(s) would work. He understands the odd lot will demand a premium, but I can't talk him into a round 50MW. So, 2 pieces of energy:
1) June-Sep'02, 20MW, 5x16
2) Cal'02, 20MW, 5x16



-----Original Message-----
From: Presto, Kevin M.
Sent: Monday, October 08, 2001 11:33 AM
To: Braddock, Billy
Subject: RE: TEA - into MEAG

Ask him if Scherer 1,2,3 and/or 4 would work? Let him know that an odd lot would command a $2.50-3.00/Mwh premium on top In addition, even if we used Scherer, it would be from any one of the facilities therefore the transmission would need to be able to use any of the Scherer units as a source.

-----Original Message-----
From: Braddock, Billy
Sent: Monday, October 08, 2001 10:21 AM
To: Presto, Kevin M.
Subject: TEA - into MEAG

TEA is looking to buy 20MW, 5x16, June-Sep'02, into MEAG. Also looking to buy 20MW, 5x16, Cal'02, into MEAG. I told them we may be more willing to offer into GTC. His response was he would need to know which facility or interface would be the source (I suspect this is so he can reserve ahead to use his network transmission).

Any interest?