Subject:Lowell, MA O&M Estimate
Cc:
Bcc:
Date:Wed, 16 Feb 2000 04:54:00 -0800 (PST)

Ben, please find attached below the preliminary O&M cost estimate for O&M
services to mobilize and operate the 4 x LM6000 peaking facility to be
situated at an existing UAE cogen plant in Lowell, Mass. It assumes some
allocated costs for common facilities, operating/admin expenses and staff at
the UAE plant to be added to the incremental expenses that are estimated to
occur as a result of the plant addition. Please review it and consider its
accuracy to be +/- 25%. Call if you have any questions.
---------------------- Forwarded by Scot Chambers/ENRON_DEVELOPMENT on
02/16/2000 12:06 PM ---------------------------


Scot Chambers
02/15/2000 08:09 PM
To: Mark Dobler/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Tom
Callaghan/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, David
Ehler/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Mitch
Robinson/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, John W
Cates/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, Richard
Bickings/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT
cc:

Subject: Lowell, MA O&M Estimate

Please review the attached O&M estimate for the Lowell, Massachusetts 4 x
LM6000 peaking facility to be situated at an existing UAE cogen plant. UAE
will own and operate the plant and ENA will have option on the output for
about 3 to 5 years. The O&M cost estimate shown assumes the hire of 2 O&M
techs to cover the LM6000 plant for the 2 peak period shifts. Current staff
at UAE plant is reported as 7 total (including admin) which seems low for a
cogen, so I've shown the addition of 2 techs. It assumes an allocation of
some existing labor and admin/operating costs from the existing plant, but in
no case is the "annual total" for the fixed costs more than 1/2 of what we
could do it for ourselves if it was "stand alone". Maintenance and chemicals
are shown as variable. The fees are shown for what we used for the Wilton
Center Expansion ($40M - Mob; $80M - Annual Ops).



thanks, Scot