Ben, please find attached the preliminary cost estimate for full O&M services
provided at one greenfield, stand alone 2 x LM6000 PC Sprint simple cycle power project located at St Peter, Illinois. The project is assumed to be 100% gas-fired and operating 1,600 hrs per year in the months of May through September. The staffing plan does not anticipate operations during the other months of the year. The tentative schedule is NTP 9/00 and COD 6/01. Ameren is to own and operate. A couple of questions: 1. Where is Ameren's headquarters located, i.e. the home office where their O&M staff would get their admin, technical support? 2. Who will own and operate the same plant that Spectrum is building 20 miles to the north of St Peter? Please review and call should you have questions or comments. regards, Scot
|