![]() |
Enron Mail |
Attached is a revised and updated 2000 Weekly Cost Report. Please review the
changes, which I have summarized below, and call if you have any questions. Thanks Amy 3-7805 1. For the Wilton and Gleason projects, the Current Forecast was overstated by the amounts paid to Nepco on April the 28th. This resulted in a significant erroneous variance of about $27 million. In other words, I didn't reduce the forecast by the amount of the payment. 2. The unapproved Acceleration Scope change on Lincoln, approximately $14 million , has been broken out separately to be consistent with the other 2 projects as a separate variance explanation. 3. The EECC Fixed Fee of $3 million per project has been removed from both the Original Budget and Current Forecast. as requested by Dave Delainey.
|