Attached please find the weekly cost report. The only material change is a
reduction in Gleason Start-up Fuel/Power. A credit for the sale of power was not booked against the project until after closing. I am working with Ben Jacoby, Fred Mitro, and Chris Booth to review Estimate to Complete and Total Projects. We are focusing in on a couple of areas, one being the Westinghouse Turbines. We have withheld money for Liquidated Damage claims for both Wheatland and Gleason. Additionally, we have scheduled the final Nepco audit for August 28th - 30th. We will be reviewing actuals, estimate to complete and ultimately the final forecast. Please call if you have any questions. Thanks Amy 3-7805
|