---------------------- Forwarded by Don Miller/HOU/ECT on 10/28/2000 03:31 PM
---------------------------


Linda L Lawrence@ENRON
10/27/2000 09:46 AM
Sent by: Linda L Lawrence@ENRON
To: Stuart Zisman/HOU/ECT@ECT, Don Miller/HOU/ECT@ECT, Christi L
Nicolay/HOU/ECT@ECT
cc: Larry Soderquist/HOU/ECT@ECT, Leslie Hansen/HOU/ECT@ECT, Sheila
Tweed/HOU/ECT@ECT
Subject: Re: Indiana Peaking Plant

Attached are the interconnect agreements requested below, if you cannot
access, please let me know.

Thanks
Linda
36872







Christi L Nicolay@ECT
10/26/2000 06:41 PM

To: Stuart Zisman/HOU/ECT@ECT
cc: Leslie Hansen/HOU/ECT@ECT, Sheila Tweed/HOU/ECT@ECT, Larry
Soderquist/HOU/ECT@ECT, Don Miller/HOU/ECT@ECT, Linda L
Lawrence/NA/Enron@Enron
Subject: Re: Indiana Peaking Plant

Stu--Both were filed with FERC. The remote control agreement was filed on
5/8/00 ER00-2447. The interconnection agreement was also filed with FERC,
however, the FERC website just went down. I will be out in the morning, so
if you need the interconnection agreement between Westfork and Indianapolis
Power & Light, please call my para legal Linda Lawrence 36872 to pull for
you.


From: Stuart Zisman on 10/26/2000 06:24 PM
To: Leslie Hansen/HOU/ECT@ECT, Sheila Tweed/HOU/ECT@ECT, Christi L
Nicolay/HOU/ECT@ECT, Larry Soderquist/HOU/ECT@ECT
cc: Don Miller/HOU/ECT@ECT

Subject: Indiana Peaking Plant

On a conference call today dealing with the sale of the Wheatland, IN peaking
facility, I was asked whether either the IPL Interconnection Agreement or the
Remote Control Operating Agreement with IPL was(or should have been) filed
with/approved by the FERC. Do any of you have any insight into this issue?
I was not involved in either of these agreements. Please advise ASAP. Many
thanks.

Stuart