Ben,
I spoke to Ross Newlin regarding the vibration problems. The Westinghouse engineers corrected the problem to the point that it was below alarm limits. There is no plan to repair the problem during the November outage since it requires significant run time and the economics are not there for a November run. However, West. has committed to come back to the plant in January when we can schedule some run time. Ross will try to track down the minutes of the outage planning meeting to document this. I'll forward them to you when I get them. Rick Benjamin Rogers@ECT 10/25/2000 10:36 AM To: Richard Broussard/Corp/Enron@Enron cc: Subject: Rick: Here are some questions we are working on where we need a little assistance. Check question 2.14 and any others. Thanks! Ben
|