Enron Mail

From:ron.coker@enron.com
To:louis.iaconetti@csfb.com
Subject:Responses to PG&E Questions on Pastoria
Cc:andrew.kelemen@enron.com, benjamin.rogers@enron.com, don.miller@enron.com
Bcc:andrew.kelemen@enron.com, benjamin.rogers@enron.com, don.miller@enron.com
Date:Tue, 26 Sep 2000 05:23:00 -0700 (PDT)

I am working with Don Miller and will be responsible for receiving and
processing all due diligence requests for Pastoria.

Below are our responses to PG&E's questions:


QUESTION:Is the major maintenance reserve estimate based on a negotiated Long
Term Services Agreement (LTSA)? If so, will it be in place and transfer with
PEF?

RESPONSE: We have not negotiated an LTSA with anyone at this time, and we do
not expect to have one in place to transfer with PEF. The maintenance
reserve is our estimate based on industry data and information from GE.


QUESTION: Are spare parts for the first major overhaul included anywhere in
the capital cost estimate or are they assumed to be purchased through the
maintenance reserve estimate (i.e. the LTSA) charge?

RESPONSE: The maintenance reserve is intended to include parts and labor for
the overhaul.


QUESTION: What is Enron's intent re: continuing involvement? PG&E is
concerned about any potential requirements that they might be required to
either purchase fuel from Enron or engage Enron as the power marketer.

RESPONSE: Enron is very flexible re continuing involvement: scheduling
coordination, fuel supply, power marketing, etc. We are also flexible re the
time period and the terms of the continuing involvement. Whatever
arrangement is developed would be mutually beneficial.


QUESTION: What is status of EPC negotiations. Will they be required to
engage NEPCO as the EPC contractor? Does the EPC contractor have control
over the turbines?

RESPONSE: o EPC negotiations are complete with NEPCO. Contract has not been
executed, but has been "put on the shelf" awaiting decision on successful
bidder for the purchase of the Pastoria project from ENA. Successful bidder
and NEPCO will each have the option of executing the EPC agreement.

o The successful bidder will be under no obligation to engage NEPCO.

o Pastoria has control of the turbines.


QUESTION: They also questioned whether there would be any "agricultural
restrictions"?

RESPONSE: The project site is presently under a Williamson Act contract to
maintain agricultural use in exchange for lower taxes. Last week, the Kern
County Board of Supervisors voted to cancel the Williamson Act contract to
allow for industrial use, which started a 180-day public comment period.
However, the Governor has on his desk a bill for signature that would reduce
the public comment period for the cancellation to the same time frame as the
request for rehearing period for the CEC Final Decision. (The Governor has
until 9/30 sign the bill and is expected to do so because of the overwhelming
support of the bill in the Assembly and the Senate.) The cancellation will
be contingent upon a successful CEC decision and a payment of a Williamson
Act cancellation fee.


QUESTION: I received a call from Tom Favinger at PG&E today. He would like
to get a breakout of the $10.25 million item in the Pastoria capital budget
labeled Pre-Commercial Operations Costs.

RESPONSE: The breakdown (in $MM) is as follows:

Project management during construction $1.000
Start-up and acceptance 2.900
Insurance and performance bond 1.846
Owner's Engineer 1.500
County Chief Building Officer/Engineer/Consultant 3.000

TOTAL $10.246


Should you have any questions, please call me at 713.345.8992.