Enron Mail

From:don.miller@enron.com
To:benjamin.rogers@enron.com
Subject:Update - Responses to Wheatland Questions
Cc:
Bcc:
Date:Sun, 22 Oct 2000 11:18:00 -0700 (PDT)

---------------------- Forwarded by Don Miller/HOU/ECT on 10/22/2000 06:17 PM
---------------------------



From: Richard Broussard @ ENRON 10/20/2000 12:30 PM


To: Don Miller/HOU/ECT@ECT
cc: Mitch Robinson/Corp/Enron@Enron
Subject: Update - Responses to Wheatland Questions

Don,

For response #3, I have additional comments:

The ambient conditions were such that output was limited by the MW limiter in
the WDPF. Unit #3 was only operated at 96.2% of base load. Since the
guarantees were met during the test, no additional testing was done.

Rick

---------------------- Forwarded by Richard Broussard/Corp/Enron on
10/20/2000 12:25 PM ---------------------------

Enron North America Corp.

From: Richard Broussard 10/20/2000 12:15 PM


To: Don Miller/HOU/ECT@ECT
cc: Mitch Robinson/Corp/Enron@Enron

Subject: Responses to Wheatland Questions


1. The correction curves are not published with the Test Reports. The
calculations are given using the correction data only. The curves and
detailed explanations are located in the purchase contracts.

2. The run hours are estimated based on the emissions limits, the guaranteed
emissions output of the equipment and average heat rates.

For example at Wheatland:

The NOx cap is 249 tons/year * 2000 = 498,000 lbs./yr. (permit limits)
The NOx output of each unit is 0.092lbs /MMBtu (Mfg. guarantee)
The Fuel Use is 1,486 MMBtu/hr HHV (Based on avg. heat rate)
NOx /hr = 0.092 lbs/MMBtu * 1,486 MMBtu/hr
= 136.7 lbs/hr.

Plant NOx = 136.7 lbs/hr * 4
= 546.8 lbs/hr

Run Hours = 498,000 lbs/hr / 546.8 lbs/hr
= 911 hrs.
These numbers are approximate and are conservative.

3. Regarding the performance issue with Wheatland Unit#3; I did find a
reference in the test report stating that units 3 & 4 were underfired due to
the MW limiter in the WDPF. Unit 3 was loaded at only 96.2% of base load and
Unit 4 at 98.4%. This along with Mitch's comments (The output guarantee was
for the facility and each unit could have been fine tuned differently) more
than likely contributed to the output differences.

4. The gas pressure issue at Wheatland in June was a one time excursion per
Chris Norris. There have been no pressure problems since then.

Rick