Subject:Up-date on situation with Enron's physical and financial deals in
Cc:
Bcc:
Date:Mon, 21 Feb 2000 03:31:00 -0800 (PST)

Cc: michael.brown@enron.com, joe.gold@enron.com, roy.poyntz@enron.com,
ross.sankey@enron.com, reuben.maltby@enron.com
Mime-Version: 1.0
Content-Type: text/plain; charset=us-ascii
Content-Transfer-Encoding: 7bit
Bcc: michael.brown@enron.com, joe.gold@enron.com, roy.poyntz@enron.com,
ross.sankey@enron.com, reuben.maltby@enron.com
X-From: Mark Elliott
X-To: Richard B Sanders, Jeffrey T Hodge
X-cc: Michael R Brown, Joe Gold, Roy Poyntz, Ross Sankey, Reuben Maltby
X-bcc:
X-Folder: \Richard_Sanders_Dec2000\Notes Folders\All documents
X-Origin: Sanders-R
X-FileName: rsander.nsf

Richard / Jeff,

To give you an up-date on certain specific non-deliveries / non-payments in
the Dutch power market, I would report as follows:

1. Non-deliveries of physical power by Enron to various counterparties

I understand that Enron re-commenced deliveries to our counterparties
approximately 10 days ago. This was because Enron was allowed to contract
domestic power in the Netherlands in a process from which Enron had peviously
been excluded. The long and short of it is, however, that we are now only
dealing with the historical non-delivery situation, i.e., our disputes over
the amounts invoiced to us for non-delivery. Please note in this regard:

Re. non-deliveries to REMU: REMU were billing us everday for non-deliveries
at superpeak prices (i.e., 577 Euros / MWh or higher) for all hours. We
disputed properly all those bills under the invoice dispute procedures set
out in our contract on the basis that we believe that we did not fail to
supply all hours and / or the prices for the hours when we did fail to supply
were not always at superpeak. The portions of their invoices which we did
not dispute, we paid in due form.

We have not received any bills from them since on or about 7th February. The
disputed amount of their previous invoices amounts to $1.6M. Initally, REMU
did not try to agree with us what the figure should be, despite our
invitations to them to discuss the issue with us. Commercial met with REMU
during the week before last to discuss the issue and REMU were still in the
process of deliberating what the figure should be. However, they now tell us
that they will claim full damages (and not just cover damages) against us and
will send us an invoice next week in this regard. We have written to them
formally to deny their claims in this regard.

In addition, please note that REMU decided not to pay Enron $0.8M in
January with regard to deliveries which we made to them in December '99 - on
the mistaken assumption that they could payment net that against their
non-delivery claims. We sent REMU last Friday a notice requiring payment for
December deliveries and reserving all our rights on this issue (my
instructions from Commercial until last Friday were not to send this notice
as it might have jeopardised the delicate negotiations over the amounts which
we truely owe them on our non-deliveries). On the basis of their current
stance (i.e., to claim full damages against us, etc), I secured Commercial's
consent to send the notice. Commercial also mentioned this non-existence of
a legal basis to withhold the January payment when they met REMU during the
week before last.

Re. non-deliveries to ENECO: We disputed a couple of their invoices in
accordance with contractual provisions as per REMU''s above. They claim that
they then sent us a letter (a copy of which we never received to the best of
our knowledge and, in fact, a copy of which they have since failed to provide
us, despite our requests) claiming that we were in default under the contract
- although not actually closing us out. Clearly we do not know what their
letter which failed to arrive said nor have they been able to explain it
verbally. Hence we are waiting for a copy of the missing letter. Value of
remaining contract $ -5 M

Re non-deliveries to Westland & Maastricht: They have not invoiced us yet -
counterparties relaxed - Commercial discussing reasonable cover damages
payment to these counterparties for our previous non-deliveries.

2. Non-payments of monies owed to Enron on swaps

Last year we bought (i.e., we receive floating price) some whole year 2000
swaps, the underlying reference price source being the APX, from these
counterparties:

Electrabel
Bayernwerk
Norsk Hydro

First payment date on all the swaps was 7.2.2000 - none of them have paid us.

Electrabel (cries of "APX has been rigged", etc., etc.,) wants to escrow the
money which they we to us. We have written to them under the ISDA Form,
crystallising their default date as at close 11th February and reserving all
our rights. Clearly, we have also refused to allow them to place the money
they owe us on escrow and that they should pay it to us forthwith (approx.
Euros 5.2m for January). Commercial having reasonable discussions with
Electrabel on this matter at present - hence we are not closing them out at
this stage (although we have reserved all our rights). Signed Deemed ISDA
confirm for this deal, thus no dispute over the deal per se.

Bayernwerk - mainly using the old chestnut "we didn't sign your confirm and
you didn't sign ours - hence no deal" (total nonsense in law).
Correspondence gone back to them telling them that their excuses aren't
legally valid and to pay up, reserving all our rights. There is a query over
whether ISDA Form would or would not apply to this deal - even if it was not
to apply, they are still liable for debt or for anticipatory / repudiatory
breach of contract (as they have told us that they won't pay as the do not
acknowledge that the swap exists owing to no confirm signed between the
parties (although they acknowledge the terms of the deal!!)). Payment due to
us on 7.2 2000 was $0.5 M. Value of entire contract to us $ 1.5 M. We have
reviewed the tapes etc - and it is pretty clear that we are in the right.
Joe Gold has given us the green light to sue Bayernwerk - instructions have
gone out to Ed Patton at Clifford Chance to commence proceedings.

Norsk Hydro (last couple of days) - we understand that they acknowledge that
a swap was done (conversation between Commercial and Norsk Hydro of yesterday
on tape) but that they didn't want to pay on account of adverse market
conditions!! Default letter gone out to them, and Joe Gold has given us the
green light to sue them - instructions have gone out to Ed Patton at Clifford
Chance to commence proceedings. Payment due to us on 7.2.2000 was $ 0.5M.
Value of entire contract to us $ 2.5 M.

3. Amounts Enron owes to swap counterparties

Note that all payments for January were made to counterparties by Enron
relating to all our swap contracts where we had sold floating price being the
APX for 2000. Evidence gathering still going on re those counterparties who
we know rigged the market to check whether we have a strong enough case to
win court actions should we not pay them on the swaps later on and get sued.

Kind regards

Mark