Enron Mail

From:nicholas.o'day@enron.com
To:richard.shapiro@enron.com
Subject:EPower Regulatory situation
Cc:
Bcc:
Date:Tue, 1 May 2001 04:06:00 -0700 (PDT)

FYI
---------------------- Forwarded by Nicholas O'Day/AP/Enron on 05/01/2001
10:56 AM ---------------------------


Nicholas O'Day
04/30/2001 12:01 PM
To: John Sherriff
cc:

Subject: EPower Regulatory situation

John, after two preliminary meetings with EPower project managers on
regulatory issues and several discussions with Carey, it is clear that a lot
of work needs to be done on the regulatory front for EPower. For a start, we
need to go back and address the fundamentals:
the implications of Japan's deregulating market on forward power prices
the permits required for construction and operation of power plants and
related facilities, and the time needed to obtain those permits
the ability to access the transmission network at the preferred sites in a
timely and cost effective manner

Over the next few weeks, I will be undertaking a comprehensive regulatory
review and will develop a lobbying strategy to address each of the barriers
to timely development of EnCom's projects. Having said that, there is a real
possibility that the permitting process cannot be shortened within an
acceptable time frame, or that an assessment of forward power prices suggests
that under certain scenarios it would be uneconomical to proceed with
development of one or more of the projects.

Forward Power Prices. EPower is currently using a projected forward power
price for 2007 and beyond based on the price paid by TEPCO to IPPs in
1995/96. Deregulation is inevitable in Japan and international experience
suggests that a period of significantly lower wholesale power prices will
likely follow, particularly given that Japan is likely to be in generation
surplus until at least 2010.

Permitting. EPower has indicated that it recently discovered that the
permitting process for Aomori project will take 7 years to complete, without
a significant lobbying effort. Prior to that, EPower believed that permitting
would take 3 years. Again, EPower based the 3 year permitting estimate on the
estimates of bidders in the 1995/ 96 IPP program. However, most of the IPP
proposals involved repowering of existing plants which reduced the permitting
time. In addition, the IPP program commenced prior to the introduction of the
current environmental laws.

Transmission Access. EPower has said that Chugoku Electric advised them that
it will take approximately 10 years and in the order of US$200m to connect
the proposed Ube plant to the transmission system. In addition, we have
preliminary indications that Tohoku Electric are looking at a similar time
frame to connect the Aomori project to the grid.

We have already started to address the transmission access issue. EPower
acknowledges that it needs a better understanding of the dynamics of the
transmission system to address in a meaningful way the concerns raised by the
utilities on connection to the transmission system. Both EPower and Enron
Japan have sufficient primary information on the transmission system for
David Mason in the London office to develop a dynamic model. Armed with the
information from the model, together with a more thorough understanding of
the rules of connection to the transmission system, we aim to be in a
position to negotiate in a more meaningful way with the relevant utilities.

Project Valuation. These issues have a direct bearing on what I understand
EnCom's value proposition to be - to take first mover advantage in Japan to
build, own and operate power plants in Japan more efficiently than the
incumbents. After almost twenty months operating in Japan, it may be timely
for EnCom to review this proposition.

I have proposed to Carey that in conjunction with the regulatory review that
he arrange for a reassessment of Encom's projects using a robust and
objective approach with input from Ariga (Domestic plant development), Andy
Foote/ Ed Cattigan (International plant development) and Jane McBride
(legal). As part of that reassessment, I have suggested that EPower price the
typical risks associated with project development - financing, construction,
commodity, operating, market, legal, regulatory and political risk with a
view to making a financial assessment of each project on a best case, worst
case and mid case scenario.

The aim is to lay all the development risks out now so that we can make an
informed decision on projects and quickly assess the implications of events
as they arise through the course of project development.

John, it would be good to talk about these issues prior to the EPower
conference call on Wednesday. Today is a holiday in Japan, but feel free to
contact me at home or alternatively, I will be in the office Tuesday. My
contact numbers are as follows:

Work 813 5219 4583
Home 813 52610539
Mobile 8190 2733 4795

kind regards