Please find below the GTV project status update for this week. Please see the attached file for the project timeline update in Microsoft Project.

GTV status meeting attendees: Dave Nommensen, Karima Husain, Francis Lim, Jeremy Wong, Bill Fortney, Nayan Dattani, Russ Severson, Narasim Kasaru, Mike Swaim, Chuck Ames, Jay Krish.

Accomplishments:

? Incorporating physcial deal positions in TDS:
o Changes to CPR reader process & its unit testing have been completed.
o Loading prior-day curves into position manager has been completed.
o Changes for the view aggregation have been completed (please see the attached project timeline).

? Single point of deal entry for term deals:
o Single point of deal entry is in user testing with some minor corrections being made as detected.

? Gas Daily deals:
o Changes to PortCalc application to create GDI calc in ERMS are complete and ready for testing.
o IT development items are in progress and on schedule (please see the attached project timeline).

? Live feeds for Gas Daily/intra-month curves:
o Development of live feeds has been completed, tested, user-approved and already in production.

? Option Grid (phase 2):
o Conversion from Motif into Powerbuilder is in progress.

? Gas Daily options:
o Changes to PortCalc application have been completed; waiting for user acceptance testing.

Plans for the week ending 5/4/01:

? Continue IT development of Phase I items.
? Continue IT development of Phase 2 issues.

Issues / Open Items:

? To be determined: whether "group of groups" on Cash Positions must be included in the rollout.
? To be determined: whether Cash Total needs to be included in Position Manager rollout (and how).
? Excluding the above 2 items, rollout to production is planned for mid-May.