Enron Mail |
Please see below for the weekly status report for the GTV project and please see the attached file for the updated project timeline.
GTV status meeting attendees: Zhiyong Wei, Russ Severson, Francis Lim, Jeremy Wong, Bill Fortney, Chuck Ames, Geoff Storey, Karima Husain, Jay Krish, Mike Swaim, Nayan Dattani, George Grant, Narasim Kasaru. Accomplishments: ? Incorporating physcial deal positions in TDS: o Changes for the view aggregation have been completed. o Expandable Total in Cash Position on schedule (please see the attached project timeline). ? Single point of deal entry for term deals: o Phase 1 of single point of deal entry for term deals is in user test. ? Gas Daily deals: o Revisions for changes to PortCalc application to create GDI calc in ERMS have been worked on. ? Live feeds for Gas Daily/intra-month curves: o Released to production. ? Option Grid (phase 2): o Released to production. ? Gas Daily options (phase 2): o Changes to PortCalc application have been completed and in user test. o The Option Delta Change Forward Month report has been completed and in user test. ? Basis Options (phase 2): o Development of deal entry type for Basis Options complete in TAGG. Plans for the week ending 5/25/01: ? Continue IT development of Phase I items. o Changes to PortCalc for valuing physical outer month positions. o Some modification to GDI Calc. o Changes to curve shift report for GDI Calc. o Expandable Total in Cash Position. ? Continue IT development of Phase II issues. Issues / Open Items: None Thanks Zhiyong
|